Technical centre
Project approval date: 2010-10-26
Project location: Kitwe
Project description:
Construction d’un Centre Technique Régional à Kitwe, Livingstone.
Goal project number: 4
Project status: Active
Objectives:
Déconcentration des Centres de Formations pour Jeunes de la FAZ.
Développement des capacités d’hébergement pour des formations.
Acquisition du matériel pour les formations théoriques.
Développement des aires de jeu existantes pour les formations pratiques (pelouse naturelle).
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
Technical centre
Project approval date: 2007-03-21
Project location: Lusaka
Project description:
Second pahse of the National Tecnical Centre
Goal project number: 3
Project status: Active
Objectives:
To complete the actual tecnical Centre
To improve the capcity of the MA to establish development programs in particular for the youth and women's football.
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| ASESCO | 347743 |
| Adam Hood Quantity Surveyors Ltd | 13444 |
| Bicon Zambia Limited | 17756 |
| Design Workshop ( TDW) | 17375 |
| Total paid | 396318 |
Technical centre
Project approval date: 2004-09-22
Project location: Lusaka
Project description:
National Technical Center fot the Football Association of Zambia
Goal project number: 2
Project status: Active
Objectives:
To provide a Camp House which has comfortable accomodation for the national teams., and teaching and meeting rooms
| Goal contribution | 399131 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 399131 |
| Contractors | Total amount |
|---|---|
| Adam Hoods and Partners | 13913 |
| Anderson+ Anderson International | 16522 |
| ASESCO Limited | 347826 |
| Bicon Zambia Limited | 20870 |
| Total paid | 399131 |
Headquarters
Project approval date: 2001-07-04
Project location: Lusaka
Project description:
National association headquarters in Lusaka.
Goal project number: 1
Project status: Active
Objectives:
To have an own house of football.
To coordinate all activities of the MA in an efficient way in one central location.
| Goal contribution | 400000 |
| FAP contribution | 70001 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 555001 |
| Contractors | Total amount |
|---|---|
| Anderson/Ander | 30013 |
| Adam Hood | 19532 |
| Bicon Zambia | 29060 |
| China Jiangxi | 391396 |
| Total paid | 470001 |