Headquarters, Other

Project approval date: 2011-02-28

Project location: Newport International Sports Village

Project description:
Completion of the construction of the Headquarters and National Technical Centre in Newport International Sports Village.

Goal project number: 2

Project status: Active

Objectives:
• Centralise headquarters and administrative offices for the Welsh football association
• Build a centre of excellence for football education and sports science

Goal contribution500000
FAP contribution0
MA contribution4937789
Other contribution0
Total budget5437789

Technical centre

Project approval date: 2003-05-01

Project location: Vale of Glamorgan

Project description:
National training centre in cooperation with Leekes Ltd. The project includes changing rooms, a medical clinic, fitness rooms, a storage room and accommodation

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
- to enable the association to use the technical centre for the training of its youth and national teams
- to reduce costs

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Wales FF400000
Total paid400000