Project approval date: 2013-03-18
Project location: Chapuis Stadium, Luganville, Espirito Santo, Vanuatu
Project description:
Construction of education & conference centre, administration offices, changing rooms and playing fields
Goal project number: 5
Project status: Active
Objectives:
- to provide essential infrastructure and additional facilities at Chapuis Stadium to broaden football activities & programmes for players at all levesl (boys & girls / men & women)
- to service the needs of the northern group of the islands stakeholders in particluar for talented youth players (age 13 -15)
- to provide further facilites primarily for football education
- to generate additional reveneu tragetinig community groups & other sports/provincial government organizations
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
Technical centre
Project approval date: 2009-12-01
Project location: Port Vila
Project description:
Completion of the work initiated under previous Goal projects at the national football academy. The project includes: a caretaker’s residence, players’ accommodation, a recreation hall, changing rooms, a futsal pitch, upgrading of a natural turf pitch and security fencing. The project also includes the construction of a regional technical centre in Santo
Goal project number: 4
Project status: Active
Objectives:
The objectives of this project are:
-to provide additional infrastructure to meet the needs of the residential national academy U-17 talented player programme
-to implement phase I of the renovation of Chapuis Stadium as the northern region technical centre
- to train and prepare regional squads identified as possible national team players
-to facilitate a residential U-15 talented player development programme with universities
-to upgrade playing surfaces for training and competition
-to implement education courses and programmes for coaches, administrators and sports medicine personnel
| Goal contribution | 400000 |
| FAP contribution | 70680 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 470680 |
| Contractors | Total amount |
|---|---|
| KD Entreprise, Luganvill | 130500 |
| Franconieri and Son Construction | 302113 |
| Alain Agobian (Architects) | 13567 |
| Mainguy Consulting Engineer & Project Management | 8000 |
| Total paid | 454180 |
Football academy
Project approval date: 2008-10-22
Project location: Port Vila
Project description:
Establishment of a national U- 17 player development academy
Goal project number: 3
Project status: Active
Objectives:
The objectives of this project are:
-to identify, train and prepare talented U-17 players in a full-time academy environment (2-year programme)
-to provide secure and adequate infrastructure to meet the needs of the players’ development
-to provide football equipment and clothing for training and competition programmes
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| 2nd instalment 2010 (Q2) | 36980 |
| Don Taileur | 7374 |
| 2nd instalment 2009 (3rd quarter) - ADO Aukland technical mission | 1400 |
| Vanuatu Agricultural Supplies Ltd | 3014 |
| Vuksich & Borish (NZ) Ltd | 46030 |
| 1st instalment 2010 (Q1) | 44691 |
| 1st (and final) instalment 2011 | 45556 |
| 2nd instalment 2009 (3rd quarter) | 50310 |
| GSM International Pty Ltd | 5668 |
| EARTHQUIP Ltd | 21300 |
| 3rd instalment 2010 (Q3) | 54840 |
| Pactec | 9226 |
| 1st instalment 2009 (1st quarter) | 73610 |
| Total paid | 399999 |
Technical centre
Project approval date: 2007-03-21
Project location: Port Vila
Project description:
Completion of the work initiated under Goal project I. The project includes: players’ accommodation, a medical clinic, a laundry room, external dining facilities, upgrading two natural turf pitches, changing rooms, football equipment and furnishings
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
-to provide adequate facilities to accommodate residential player development programmes
-to train and prepare the national teams at all levels
-to facilitate a residential U-17 talented player development programme
-to improve the existing football facilities for training and competition programmes
-to implement education courses and programmes for coaches, administrators and sports medicine personnel
| Goal contribution | 399364 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 399364 |
| Contractors | Total amount |
|---|---|
| Eric Ernest Bourdet | 4560 |
| Qualao Consulting Limited - ‘consultancy’ basis | 217 |
| Entreprise Traverso Sandrino | 394062 |
| Qualao Consulting Limited - ‘consultancy’ basis | 525 |
| Total paid | 399364 |
Technical centre
Project approval date: 2001-07-04
Project location: Port Vila
Project description:
National Football Academy first phase of the construction of the technical and administration offices. The project includes: an education centre, a kitchen and dining room, bathrooms, two natural turf pitches and security fencing
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
-to establish facilities for the delivery and administration of technical activities football pitches and buildings
-to improve the association’s technical programmes and courses
- to facilitate additional competitions for youth and women’s teams
-to increase opportunities for youth players to participate in organised elite player development programmes
-to facilitate training programmes for national team players
| Goal contribution | 400000 |
| FAP contribution | 39267 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 439267 |
| Contractors | Total amount |
|---|---|
| Entreprise Traverso Sandrino | 300300 |
| Debit of Legal Fees | 0 |
| Eric-Ernest Bourdet, Architect | 15767 |
| SPIE-EGC (SPECIAL CASE) | 123200 |
| Total paid | 439267 |