Technical centre
Project approval date: 2010-03-15
Project location: Jinja,
Project description:
Finalisation (second phase) of the National Technical Centre of the Uganda Football Association in Jinja, Uganda.
Goal project number: 3
Project status: Active
Objectives:
To improve the capacity of the National Technical Centre.
Construction of a wall to protect the playing fields.
To construct of car parkings for the visitors of the Technical Centre.
Equipment for the Technical Centre (Fitness room, accomodation, kitchen, leisures)
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| Waed Engineers Limited | 33854 |
| FUFA | 35415 |
| Byuba Limited | 330730 |
| Total paid | 399999 |
Technical centre
Project approval date: 2006-12-03
Project location: Ginga
Project description:
National tecnical Centre
Goal project number: 2
Project status: Active
Objectives:
To improve the capacity of the MA to establish development programs in particular for the youth and women's football.
| Goal contribution | 400000 |
| FAP contribution | 14075 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 414075 |
| Contractors | Total amount |
|---|---|
| MS Allied Tec Engineers and Contractors Ltd | 329855 |
| Postmodern Consultants LTd | 24719 |
| Kyebaja Company limited | 59500 |
| Total paid | 414074 |
Headquarters
Project approval date: 2011-07-04
Project location: Kampala
Project description:
National association Headquarters in Kampala.
Goal project number: 1
Project status: Active
Objectives:
Better organisation and administration
Necessary infrastructure for meetings and technical courses
| Goal contribution | 400000 |
| FAP contribution | 10520 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 410520 |
| Contractors | Total amount |
|---|---|
| Independent Gr. | 38759 |
| ZZIMWE | 325288 |
| Semmango Joseph | 46400 |
| Total paid | 410447 |