Technical centre
Project approval date: 2012-09-25
Project location: Dubai
Project description:
Civil, electrical, mechanical and decorative works at the dormitories and health club in the UAE FA Academy Hostel building.
Goal project number: 4
Project status: Active
Objectives:
The project proposal is part of a football complex (headquarters, multifunctional hall, academy hostel) that was financed through the first three Goal projects. The objectives of this project are:
- To comply with the development strategy of the UAE FA
- To have a fully integrated football infrastructure in the main complex
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
Football pitch
Project approval date: 2010-10-26
Project location: Dubai
Project description:
Installation of two natural turf pitches. The project includes: a watering and drainage system
Goal project number: 3
Project status: Active
Objectives:
The objective of this project is:
-to provide the association with adequate infrastructure for the training of national teams
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| UAE FA | 400000 |
| Total paid | 400000 |
Other
Project approval date: 2010-03-15
Project location: Dubai
Project description:
Construction of a multifunctional hall at the headquarters. The project includes: a futsal pitch, a stadium, changing rooms and service units
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
-to incorporate all football activities at the headquarters complex
-to promote futsal in the country
-to organise futsal competitions
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| Petra Project Management | 25000 |
| United Arab Emirates Football Association | 375000 |
| Total paid | 400000 |
Other
Project approval date: 2003-05-01
Project location: Dubai
Project description:
Construction of two floodlighting systems in a technical centre. The project also includes: external walls
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
-to enable the association to improve the development of its various football teams
| Goal contribution | 400000 |
| FAP contribution | 1037837 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 1437837 |
| Contractors | Total amount |
|---|---|
| Petra Project Management | 150273 |
| United Arab Emirates Football Association | 180328 |
| United Arab Emirates Football Association | 1107236 |
| Total paid | 1437837 |