  • Project approval date: 2011-10-18
  • Project location: Dili
  • Project description:
    Extension of the technical centre. The project includes: a perimeter wall and an artificial turf pitch
  • Goal project number: 4
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to provide security for the facility
    -to limit public access
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution58860
Total budget500000
ContractorsTotal amount
Dolfin Unipessoal Lda.128835
Valley Consultant6000
Greenfields248000
Total paid382835

Football pitch

  • Project approval date: 2011-02-28
  • Project location: Dili
  • Project description:
    Installation of an artificial turf pitch
  • Goal project number: 3
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to provide a venue for the training of the national teams and other football activities
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Greenfields500000
Total paid500000

Technical centre

  • Project approval date: 2009-06-02
  • Project location: Dili
  • Project description:
    Construction of a technical centre. The project includes: dormitories, a conference room, a cafeteria and a fitness centre
  • Goal project number: 2
  • Project status: Active
  • Objectives:
    The objectives of this project are:
    -to provide a functional and modern facility for the development of the game
    -to complete and develop the previous project carried out by the association and FIFA
Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
CMG Consultant & Associates Inc,20000
China Shandong International Economic & Technical Cooperation Group Ltd380000
Total paid400000

Headquarters

  • Project approval date: 2006-03-15
  • Project location: Dili
  • Project description:
    Construction of the association’s headquarters. The project includes: administration facilities, conference rooms, management and presidential offices
  • Goal project number: 1
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to deliver headquarters and administrative offices befitting a football association
Goal contribution398000
FAP contribution0
MA contribution0
Other contribution0
Total budget495957
ContractorsTotal amount
CMG Consultant & Associates Inc20000
China Shandong International Economic & Technical Cooperation Group Ltd378000