Football pitch

Project approval date: 2001-07-04

Project location: Asghabat

Project description: Installation of an artificial turf pitch at the Kopeddag stadium

Goal project number: 1

Project status:

Objectives: The objective of this project is:
-to support the league and enable matches to take place in an adequate environment

Goal contribution400000
FAP contribution37745
MA contribution0
Other contribution0
Total budget437745
ContractorsTotal amount
Belhasa Projects437745
Total paid437745

Headquarters

Project approval date: 2004-09-22

Project location: Asgabat

Project description: Construction of the association’s headquarters
THIS PROJECT NEVER REALLY STARTED

Goal project number: 2

Project status:

Objectives: The objective of this project is:
-to deliver headquarters and administrative offices befitting a football association

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000