Project approval date: 2006-12-03

Project location: Belgrade

Project description: Construction work to complete the FSS headquarters and technical centre. The project includes: football pitches, lighting, accommodation and office rooms

Goal project number: 1

Project status:

Objectives: The objectives of this project are:
- to enable the association to use the technical centre for the training of all of its teams
- to provide the association with a functional and modern facility

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Goal I - HQ & TC400000
Total paid400000

Headquarters

Project approval date: 2009-12-01

Project location: Stara Pazova

Project description: Construction work to complete the FSS headquarters and technical centre. The project includes football pitches, lighting, accommodation and offices

Goal project number: 2

Project status:

Objectives: The objective of this project is:
- to establish a technical centre and headquarters at one site

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Execution of HQ400000
Total paid400000

Technical centre

Project approval date: 2012-03-27

Project location: Stara Pazova

Project description: Construction of spectator stands around the football pitch at the national technical centre

Goal project number: 3

Project status:

Objectives: The objectives of this project are:
- to develop women’s football through better use of existing facilities
- to help the association to optimise the use of its technical centre
- to host youth leagues, football schools and other clubs

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution3200000
Total budget3700000