Project approval date: 2013-03-18
Project location: Stadio di Serravalle, San Marino
Project description:
Demolition and reconstruction of dressing rooms and construction of a new building with 3 floors in order to provide better infrastructure for teams, referees, medical, match officials and press (conference room), meeting lounge and a physiotheraphy unit (gym)
Goal project number: 4
Project status: Active
Objectives:
Comply with all necessary requirements in order to host international matches
Provide better infrastructure for teams, referees, match officials and press (conference room)
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 341000 |
| Other contribution | 0 |
| Total budget | 841000 |
Headquarters
Project approval date: 2006-12-03
Project location: City of San Marino
Project description:
Construction work to complete the FSGC headquarters
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
- to deliver headquarters and administrative offices befitting a football association
- to allow efficient collaboration within different departments
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 600000 |
| Other contribution | 0 |
| Total budget | 1000000 |
| Contractors | Total amount |
|---|---|
| Federazione Sammarinese Giuoco Calcio | 400000 |
| Total paid | 400000 |
Football pitch
Project approval date: 2004-02-17
Project location: Dogana
Project description:
Installation of artificial turf pitches: standard and futsal sizes
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
- to maximise usage of the facility throughout the year and under all weather conditions for the training and competitions of youth teams
| Goal contribution | 400000 |
| FAP contribution | 144495 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 544495 |
| Contractors | Total amount |
|---|---|
| Realsport /Markus Keller | 3750 |
| Total paid | 544495 |