Goal projects

Technical centre

Project approval date: 2014-09-23

Project description:
• Extension & upgrade of existing Headquarters & Academy buildings which includes new accommodation, a commercial kitchen, dining facilities & sanitation.
• Construction of changing rooms, official room & grand stand for the futsal court.

Goal project number: 5

Project status: Active

Objectives:
• Provide functional, comfortable and low cost facilities for the national teams.
• Provide for an increased level of activities & competitions on the futsal court necessary facilities for players, officials & spectators.
Both parts of the project also to allow Samoa FF to generate additional revenue from football activities and other targeted (market community) groups

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000

Headquarters

Project approval date: 2012-03-27

Project location: Apia & Sava’ii

Project description:
Construction of administration and management offices for the technical centre in Sava’ii island. The project includes: an education centre, kitchen and dining facilities, player/ official and public amenities, maintenance equipment and upgrading of natural turf pitch.
The project also includes: the construction of a synthetic turf futsal pitch at the national headquarters and technical centre in Apia

Goal project number: 4

Project status: Active

Objectives:
The objectives of this project are:
-to develop facilities at regional level
-to structure Sava’ii clubs to participate in competitions for men, women, boys and girls with a strong focus on the primary and secondary schools
-to employ a football administrator and technical staff to deliver services in Sava’ii
-to provide futsal facilities at the national technical centre
-to promote and develop futsal with special attention for youth and grassroots activities

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget545545
ContractorsTotal amount
J Westerlund Construction Lim. - Regional TC Sava'ii island264906
OSM Consultants - Regional TC Sava'ii Island23550
OSM Consultants - Futsal Court Tuaniamato8080
Purchase contract with FFS23143
Qinig Dao Construction - Futsal Court Tuaniamato96540
Connor Sport Court Int.- Installation of Futsal Court Tuaniamato49882
Total paid466102

Technical centre

Project approval date: 2006-12-03

Project location: Apia

Project description:
Installation of floodlights for the main pitch at the technical centre

Goal project number: 3

Project status: Active

Objectives:
The objectives of this project are:
-to upgrade the international football pitch for night-time matches and national team training
-to increase opportunities to participate in organised competitions at all levels
-to increase capacity for local and national competition matches
-to host confederation international matches

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Vuksich& Borich NZ Ltd10000
Vuksich& Borich NZ Ltd390000
Total paid400000

Headquarters

Project approval date: 2004-09-22

Project location: Apia

Project description:
Headquarters and technical centre. The project includes: administration offices, accommodation, an education centre and dining and kitchen facilities

Goal project number: 2

Project status: Active

Objectives:
The objectives of this project are:
-to deliver headquarters and administrative offices befitting a football association
-to consolidate all activities within one complex
-to provide a comprehensive “House of Football” for the association and its affiliates
- to integrate all administration and technical staff at one location to achieve “best” management practices

Goal contribution400000
FAP contribution50000
MA contribution0
Other contribution0
Total budget450000
ContractorsTotal amount
Vuksich & Borich Ltd.40000
Vuksich & Borich Ltd.410000
Total paid450000

Football pitch

Project location: Apia

Project description:
Football pitch complex. The project includes: two natural turf pitches and changing room facilities

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
-to increase opportunities for the association to participate in organised competitions
- to facilitate local, regional and national competition matches (all categories and levels)
- to train and prepare the national teams at all levels
-to deliver elite and grassroots player development programmes

Goal contribution728000
FAP contribution199914
MA contribution0
Other contribution0
Total budget927914
ContractorsTotal amount
Samoa SFA47000
Vuksich & Borich880914
Total paid927914