Project approval date: 2012-03-27

Project location: Buftea, Mogsooaia, Contanta

Project description:
The project is divided in two parts: installation of a heating system in the Mogosoaia and Buftea training facilities and construction of a tribune inside the Gheorghe Hagi football academy

Goal project number: 4

Project status: Active

Objectives:
The objectives of this project are:
- to guarantee that the pitches are in optimum condition throughout the whole year
- to establish a modern football centre for the education and development of talented young players

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Purchase of Tribune300000
Total paid300000

Technical centre

Project approval date: 2010-03-15

Project location: Buftea

Project description:
Construction of a regional technical centre. The project includes: one natural turf pitch, two artificial turf pitches, dressing rooms, storage rooms and different facilities

Goal project number: 3

Project status: Active

Objectives:
The objective of this project is
- to enable the association to use the technical centre for the training of its football teams
- to provide more training facilities throughout the country

Goal contribution400000
FAP contribution0
MA contribution5574500
Other contribution0
Total budget5974500
ContractorsTotal amount
Execution of a Training Centre - Romanian Football Federation400000
Total paid400000

Technical centre

Project approval date: 2005-11-07

Project location: Mogosoaia

Project description:
Completion of the technical centre. The project includes: a conference room, accommodation, catering and physiotherapy room, upgrade of the existing pitches and spectator stands

Goal project number: 2

Project status: Active

Objectives:
The objectives of this project are:
- to provide a venue for the training of the national teams
- to provide a venue for the education and development of youth players

Goal contribution399667
FAP contribution0
MA contribution1000000
Other contribution0
Total budget3899667

Headquarters

Project approval date: 2001-10-29

Project location: Bucharest

Project description:
Construction of the national association’s headquarters. The project includes an auditorium

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
- to deliver headquarters and administrative offices befitting a football association

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution181
Total budget400000
ContractorsTotal amount
SC Aedificia Carpati400181
Total paid400181