Project approval date: 2012-03-27
Project location: Buftea, Mogsooaia, Contanta
Project description:
The project is divided in two parts: installation of a heating system in the Mogosoaia and Buftea training facilities and construction of a tribune inside the Gheorghe Hagi football academy
Goal project number: 4
Project status: Active
Objectives:
The objectives of this project are:
- to guarantee that the pitches are in optimum condition throughout the whole year
- to establish a modern football centre for the education and development of talented young players
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
| Contractors | Total amount |
|---|---|
| Romanian FF - Purchase of Tribune | 300000 |
| Romanian FF - Installation of Heating system for pitches | 200000 |
| Total paid | 500000 |
Technical centre
Project approval date: 2010-03-15
Project location: Buftea
Project description:
Construction of a regional technical centre. The project includes: one natural turf pitch, two artificial turf pitches, dressing rooms, storage rooms and different facilities
Goal project number: 3
Project status: Active
Objectives:
The objective of this project is
- to enable the association to use the technical centre for the training of its football teams
- to provide more training facilities throughout the country
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 5574500 |
| Other contribution | 0 |
| Total budget | 5974500 |
| Contractors | Total amount |
|---|---|
| Execution of a Training Centre - Romanian Football Federation | 400000 |
| Total paid | 400000 |
Technical centre
Project approval date: 2005-11-07
Project location: Mogosoaia
Project description:
Completion of the technical centre. The project includes: a conference room, accommodation, catering and physiotherapy room, upgrade of the existing pitches and spectator stands
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
- to provide a venue for the training of the national teams
- to provide a venue for the education and development of youth players
| Goal contribution | 399667 |
| FAP contribution | 0 |
| MA contribution | 1000000 |
| Other contribution | 0 |
| Total budget | 3899667 |
Headquarters
Project approval date: 2001-10-29
Project location: Bucharest
Project description:
Construction of the national association’s headquarters. The project includes an auditorium
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
- to deliver headquarters and administrative offices befitting a football association
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 181 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| SC Aedificia Carpati | 400181 |
| Total paid | 400181 |