Goal projects

Technical centre

Project approval date: 2014-09-23

Project description:
Extension & upgrade of existing Football Academy buildings in Lae, which includes installation of floodlights, covered futsal court, fitness gymnasium and other facilities such as commercial kitchen and accommodation rooms upgrade.

Goal project number: 4

Project status: Active

Objectives:
• Offer relevant infrastructure for football related activities which will meet the needs of PNGFA, its stakeholders and increase participant numbers
• Provide facilities for regular competitions particularly for grassroots & youth.

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000

Technical centre

Project approval date: 2011-02-28

Project location: Kimbe

Project description:
Completion of the work initiated under Goal project II. The project includes: administration and management offices, an education centre and accommodation

Goal project number: 3

Project status: Active

Objectives:
The objectives of this project are:
-to provide adequate infrastructure for residential player development programmes,
- to organise education courses and football programmes
-to deliver headquarters and administrative offices befitting a football association
- to sustain activities and maintenance of facilities
-to provide opportunities for youth players to participate in structured football activities
-to promote football in the New Britain Island region

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Timkumba Holdings Limited275590
TellComm Pacific Limited10400
Total paid285990

Headquarters

Project approval date: 2006-12-03

Project location: Lae Kimbe

Project description:
Completion of the work initiated under Goal project I. The project includes: power and water supplies, upgrading a natural turf pitch, changing rooms, an administration office and security fencing

Goal project number: 2

Project status: Active

Objectives:
The objectives of this project are:
-to ensure that the essential utilities (power and water) are available by generator/pump facilities
-to enhance delivery of management administration services to affiliates
-to establish a regional technical centre for the development of football.
-to create opportunities for youth players to participate in structured football activities
-to organise technical activities and education courses

Goal contribution399525
FAP contribution0
MA contribution0
Other contribution0
Total budget399525
ContractorsTotal amount
Vuksich & Borich (NZ) Limited120000
Kimbe Concrete Products Limited139050
Joss Builders and Design Co475
Project Supplier contract130000
Project supplier contract (purchase of turf maintenance equipment & materials)10000
Total paid399525

Headquarters

Project approval date: 2001-07-04

Project location: Lae

Project description:
Headquarters and technical centre. The project includes: administration offices, accommodation, an education centre, dining and kitchen facilities and two natural turf pitches

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
-to establish a management structure for the effective administration of football in the country
- to train and prepare the national teams at all levels
-to deliver elite and grassroots player development programmes
-to deliver national and regional educational courses for coaches, referees and administrators
-to facilitate local, regional and national competition matches

Goal contribution400000
FAP contribution218964
MA contribution0
Other contribution0
Total budget618964
ContractorsTotal amount
Designscope618964
Total paid618964