Technical centre
Project approval date: 2011-10-18
Project location: Bukidnon
Project description:
Construction of a technical centre. The project includes: a natural grass pitch, dormitories, changing rooms, lecture rooms and offices
Goal project number: 4
Project status: Active
Objectives:
The objective of this project is:
-to promote good relations between different communities
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
| Contractors | Total amount |
|---|---|
| J.T. Gamolo Construction, Valencia City, Bukidnon | 240889 |
| Red Avelino & Associates, Pasig City | 27836 |
| Total paid | 268725 |
Football pitch
Project approval date: 2011-02-28
Project location: Manila
Project description:
Installation of an artificial turf pitch at the national stadium
Goal project number: 3
Project status: Active
Objectives:
The objective of this project is:
-to provide adequate facilities for the training of the national teams
| Goal contribution | 500000 |
| FAP contribution | 787 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500787 |
Headquarters
Project approval date: 2006-12-03
Project location: Pasig
Project description:
Construction of the association’s headquarters
Goal project number: 2
Project status: Active
Objectives:
The objective of this project is:
-to deliver headquarters and administrative offices befitting a football association
| Goal contribution | 400000 |
| FAP contribution | 19213 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 419213 |
| Contractors | Total amount |
|---|---|
| Philippine Football Federation (PFF) | 192048 |
| RJ Bearis Construction Inc. | 208622 |
| Red Avelino & Associates | 18542 |
| Total paid | 419212 |
Technical centre
Project approval date: 2000-08-03
Project location: Ilo Ilo, Laguna, Negros Occidental, Cagayan de Oro, Zamboanga, Agusan del Sur
Project description:
Construction of one technical centre in Ilo Ilo and five regional technical centres. The project includes: administrative offices, reception, a dormitory and a conference room
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
-to start a broad youth development programme
| Goal contribution | 400000 |
| FAP contribution | 58046 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 458046 |
| Contractors | Total amount |
|---|---|
| joenil Lavadia | 900 |
| PFF | 2439 |
| PFF | 16444 |
| PFF | 84680 |
| Arjai | 18086 |
| Duffie Botavara | 1500 |
| Guimaras Const. | 34328 |
| PFF | 2927 |
| Equipment | 7973 |
| Armar | 17750 |
| PFF | 8789 |
| PFF | 11980 |
| Jaime C. Chaves | 919 |
| PFF | 2879 |
| Raoul Quijano | 904 |
| PFF | 19317 |
| Bertraam de Leon | 875 |
| RV Dolar | 133008 |
| Serg | 18381 |
| PFF | 6191 |
| PFF | 8620 |
| PFF | 12083 |
| Miguel Larrauri | 7980 |
| Davao | 17490 |
| Benson Chang | 18000 |
| Dalupang | 887 |
| Total paid | 458046 |