Technical centre
Project approval date: 2010-10-26
Project location: Noumea
Project description:
Completion of the work initiated under previous Goal Projects. The project includes: technical offices, an education centre, floodlights, natural turf pitches, and futsal and beach soccer facilities
Goal project number: 4
Project status: Active
Objectives:
The objectives of this project are:
-to install floodlights for all playing facilities
-to extend training and competition schedules
-to develop additional leagues and competitions at all levels without interruption or restrictions
-to facilitate additional futsal and beach soccer competitions and programmes
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 110000 |
| Total budget | 400000 |
Technical centre
Project approval date: 2008-10-22
Project location: Noumea
Project description:
Completion of the work initiated under Goal project I. The project includes: two natural turf pitches, a futsal pitch, a beach soccer pitch and security fencing
Goal project number: 3
Project status: Active
Objectives:
The objectives of this project are:
- to train and prepare the national teams at all levels
-to deliver elite youth player development programmes from U-11 to U-23 level
-to provide additional pitches to facilitate local, regional and national competition matches (all categories and levels)
-to develop additional leagues and competitions without interruption or restriction
-to facilitate the development of beach soccer
-to facilitate the development of futsal
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| E.U.R.L. Pacific Jardin Paysages (Part II of II) | 375031 |
| Total paid | 375031 |
Technical centre
Project approval date: 2008-10-22
Project location: Noumea
Project description:
Completion of the work initiated under Goal project I. The project includes: two natural turf pitches, a futsal pitch, a beach soccer pitch and security fencing
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
- to train and prepare the national teams at all levels
-to deliver elite youth player development programmes from U-11 to U-23 level
-to provide additional pitches to facilitate local, regional and national competition matches (all categories and levels)
-to develop additional leagues and competitions without interruption or restriction
-to facilitate the development of beach soccer
-to facilitate the development of futsal
| Goal contribution | 400000 |
| FAP contribution | 69525 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 469525 |
| Contractors | Total amount |
|---|---|
| SARL SIGMA INGENIERIE | 5928 |
| E.U.R.L. Pacific Jardin Paysages (Part I of II) | 461057 |
| Total paid | 466985 |
Football pitch
Project approval date: 2006-03-15
Project location: Noumea
Project description:
Installation of a football turf pitch at the national technical centre. The project includes: changing rooms and caretaker accommodation
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
- to train and prepare the national teams at all levels
-to deliver elite youth player development programmes
-to facilitate local, regional and national competition matches (all categories and levels)
| Goal contribution | 400000 |
| FAP contribution | 284291 |
| MA contribution | 0 |
| Other contribution | 199900 |
| Total budget | 684291 |
| Contractors | Total amount |
|---|---|
| Don Finlay | 7100 |
| TigerTurf NZ Ltd | 22418 |
| Vuksich & Borich (NZ) Limited | 10697 |
| Vuksich & Borrich | 843976 |
| Total paid | 884191 |