Goal projects

Headquarters

Project approval date: 2011-02-28

Project location: Managua and Diriamba

Project description:
Construction of the FENIFUT headquarters in Managua. The project includes: the upgrading of the national talent school in Diriamba and the installation of regional football pitches

Goal project number: 6

Project status: Active

Objectives:
The objectives of this project are:
-to deliver headquarters and administrative offices befitting a football association
-to modernise the talent school
-to provide football facilities to more regions in Nicaragua

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Ideas Arquitectonicas S.A. (Escuela de Talentos)95404
Ideas Arquitectonicas S.A. (Oficina de fenifut)291275
Construcciones Olivas S.A. Construosa (Rio San Juan)25000
May Lee de los Angeles Chong Guido15000
Federacion Nicaraguense de Futbol (Office equipm.)25000
Ing. Yurban Aquilino Chavarria Bravo (Sto. Tomas Chontales)25000
Total paid476679

Technical centre

Project approval date: 2009-12-01

Project location: Managua

Project description:
Completion of the work initiated under Goal projects II and III. The project includes: spectator stands, lighting, a parking area and fences

Goal project number: 5

Project status: Active

Objectives:
The objectives of this project are:
-to complete and develop the previous projects carried out by the association and FIFA
-to enable the association to use the technical centre for the training of its various football teams

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Ideas Arquitectonicas S.A.385000
May-Lee De Los Angeles Chong Guido15000
Total paid400000

Football academy

Project approval date: 2008-10-22

Project location: Diriamba

Project description:
This is a pilot project for the training of talented young players for the period 2009-2011

Goal project number: 4

Project status: Active

Objectives:
The objectives of this project are:
-to contribute to the development of new players
-to provide career opportunities for young football players from poor socio-economic backgrounds
-to develop the talent of men and women players

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Activities Sub15 & Sub17 (2010) & Equipment & Other206198
Activities Sub17 (2011) & Equipment & Other130000
Activities Sub15 & Sub17 (2009) & Equipment & Other63802
Total paid400000

Technical centre

Project approval date: 2007-12-04

Project location: Managua

Project description:
Completion of the work initiated under Goal project I. The project includes: spectator stands, bathrooms and fencing.

Goal project number: 3

Project status: Active

Objectives:
The objectives of this projects are:
-to complete and develop the previous projects carried out by the association and FIFA
-to enable the association to use the technical centre for the training of its various football teams

Goal contribution400000
FAP contribution0
MA contribution35480
Other contribution0
Total budget435480
ContractorsTotal amount
May-Lee de Los Angeles Chong Guido15000
Ideas Arquitectonicas S.A. IDEARQ S.A.385000
Total paid400000

Football pitch

Project approval date: 2004-02-17

Project location: Managua

Project description:
Installation of a natural football pitch at the national football stadium in Managua. The project includes: spectator stands and changing rooms

Goal project number: 2

Project status: Active

Objectives:
The objective of this project is:
-to provide the association with its own facilities

Goal contribution414105
FAP contribution895
MA contribution0
Other contribution0
Total budget415000
ContractorsTotal amount
May Lee De Los Angeles Chong Guido15000
Ideas Arquitectonicas S.A. IDEARQ. S.A. y/o Claudio Patricio Cuevas Ortega400000
Total paid415000

Technical centre

Project approval date: 2000-10-24

Project location: Diriamba

Project description:
Construction of the technical centre in Diriamba. The project includes: four football pitches, two futsal areas, changing rooms, a dormitory, a kitchen, a dining room and offices

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
-to hold training courses for coaches, referees and players
-to promote the development of football

Goal contribution385895
FAP contribution0
MA contribution0
Other contribution0
Total budget385895
ContractorsTotal amount
Rodriguez López20653
Nicaragua FA14462
Yubaran Bravo25949
Adolfo Miranda (old USD 24'917)7475
DATATEX (Computer Equipment Supplier - Invoice 06.12.2004)7729
May Lee Chong15000
Herrera Rivera20564
Antonio Boniche-2865
Nicaragua FA10000
Antonio Boniche4425
Herrera Rivera262502
Total paid385895