Goal Programme

Goal projects

Technical centre

  • Project approval date: 2013-09-03
  • Project location: Soccer House in Katatura in Windhoek
  • Project description:
    Additional works to complete Goal Project 3 at the Soccer House Technical Centre. Goal Project 3 largely accounted for the first phase of the Technical Centre at Soccer House in Katatura in Windhoek.
  • Goal project number: 4
  • Project status: Active
  • Objectives:
    The second phase of the NFA Technical Centre will see the completion of :
    • Erection of boundary wall
    • Upper floor of the main building, which will provide technical department offices & spectator seating
    • Lighting of football field
    • Further enhancement of MA image
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Marley Tjitjo Architects Inc.6522
Helao World (Pty) Ltd160252
Total paid166774

Technical centre

  • Project approval date: 2011-10-18
  • Project location: Windhoek
  • Project description:
    Extension of the existing Technical Centre at Soccer House in Windhoek Namibia by adding changing rooms, offices for the technical staff and a small tribune.
  • Goal project number: 3
  • Project status: Active
  • Objectives:
    To further upgrade the Technical Centre and Headquarters (Goal projects I and II) in order to:

    1) To allow for a Centre of Excellence for both girls and boys football.
    2) To provide a venue for training and camps of all National Teams.
    3) To provide a Centre for grassroots football.
    4) To provide a venue for matches at the regional level in and around Windhoek.
    5) To provide adequate facilities for the women football and junior leagues
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Helao World (Pty) Ltd444172
Marley Tjitjo Architects Inc.52522
Total paid496694

Football pitch

  • Project approval date: 2008-02-04
  • Project location: Windhoek
  • Project description:
    Installation of a Football Turf pitch in the National Technical Centre
  • Goal project number: 2
  • Project status: Active
  • Objectives:
    To complete the National Technical Centre and install a Football Turf pitch, a fence and changing rooms
    To establish development programs in particular for the youth
Goal contribution398500
FAP contribution0
MA contribution0
Other contribution0
Total budget398500
ContractorsTotal amount
Greenfields398500
Total paid398500

Headquarters

  • Project approval date: 2001-07-04
  • Project location: Windhoek
  • Project description:
    Headquarters
  • Goal project number: 1
  • Project status: Active
  • Objectives:
    Headquarters Better organisation and administration
    Necessity to have a Soccer House for the secretariat as well as technical courses and meetings
Goal contribution486000
FAP contribution198000
MA contribution0
Other contribution0
Total budget684000
ContractorsTotal amount
Pro Housing620212
CDCC23092
Geomar40696
Total paid684000