Technical centre
Project approval date: 2013-03-18
Project location: northern region of Malawi
Project description:
Additional works at the Mzuzu Technical Centre in the northern region of Malawi.
Goal project number: 4
Project status: Active
Objectives:
Although Goal Project III was successfully completed, there is need for further works to be carried out in order to give the facility a more complete feel. The works will include the following:
1) Hostel accommodation
2) Dining kitchen and laundry facilities
3) Conference / lecture room
4) Additional football pitch and dressing rooms, with public ablution blocks
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
Technical centre
Project approval date: 2010-10-26
Project location: Mzuza
Project description:
Construction d’un centre technique régional à Mzuza, au Nord du Malawi
Goal project number: 3
Project status: Active
Objectives:
Déconcentration des infrastructures pour le développement du Football au Malawi
Renforcer la présence de la Fédération dans une zone traditionnellement riche en talents et passionnée de Football
Développement de la formation et de la détection des jeunes dans le Nord du Pays
Renforcement des actions en faveur des coachs et arbitres pour les ligues du Nord
| Goal contribution | 400000 |
| FAP contribution | 175000 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 575000 |
| Contractors | Total amount |
|---|---|
| SITBEC CONSTRUCTION | 426582 |
| Technologa AEC + Design | 71291 |
| Total paid | 497873 |
Technical centre
Project approval date: 2006-03-15
Project location: Chiwembe
Project description:
National Tecnical Centre
Goal project number: 2
Project status: Active
Objectives:
To finish the existing Tecnical Centre with fields, dressing rooms, dining hall.
| Goal contribution | 400000 |
| FAP contribution | 8539 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 408539 |
| Contractors | Total amount |
|---|---|
| Barriga's Building Contractors Limited | 340776 |
| Tecknologa AEC | 57932 |
| Escom | 9831 |
| Total paid | 408539 |
Technical centre
Project approval date: 2001-07-04
Project location: Chiwembe
Project description:
Technical Centre in Chiwembe with one field
Goal project number: 1
Project status: Active
Objectives:
Training of national teams
Education of coaches, referees,
Organisation of meetings
| Goal contribution | 400000 |
| FAP contribution | 356082 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 756082 |
| Contractors | Total amount |
|---|---|
| Malawi Housing | 210545 |
| Hualong Constr. | 463053 |
| Monarch | 82484 |
| Total paid | 756082 |