Goal projects

Football pitch

Project approval date: 2011-10-18

Project location: Trianon

Project description:
Installation of an artificial turf in the Trianon Technical Centre.

Goal project number: 4

Project status: Active

Objectives:
The Trianon Headquarters and Technical Centre was the object of the past three Goal projects. The federation now proposes to transform one of the three training pitches into an artificial turf. This is justified by the following reasons:

1) Enable continued use of the facility for long hours every day
2) Reduce maintenance costs, mainly water and mowing
3) Enable players to get accustomed to artificial turf surfaces

Goal contribution500000
FAP contribution65347
MA contribution0
Other contribution88164
Total budget565347
ContractorsTotal amount
Edelgrass BV565347
Addendum contract with Edelgrass BV88164
Total paid653511

Technical centre

Project approval date: 2008-10-22

Project location: National Technical Center of Port Louis

Project description:
Develop the hosting and training facilities in the National Technical Center of Port Louis

Goal project number: 3

Project status: Active

Objectives:
- Improve the qualitity of hosting of the National Training Center
- Develop the medical and fitness follow up of the player
- improve the football equipement for preparation and training
- Improve the condition of work for technical staff an referees

Goal contribution400000
FAP contribution206
MA contribution0
Other contribution0
Total budget400206
ContractorsTotal amount
Como Construction LTD373086
RAMPHUL Associates12000
Total paid385086

Technical centre

Project approval date: 2005-11-07

Project location: Port Louis

Project description:
Completion of the Tecnical Center and Headquarters +
3 fields

Goal project number: 2

Project status: Active

Objectives:
To complete the Technical Centre : purchase of furniture to ensure full usage and completion of the facilities ( e.g. fencing and fields)
To improve working conditions for administration of the MA.

Goal contribution400000
FAP contribution99794
MA contribution0
Other contribution0
Total budget499794
ContractorsTotal amount
Rhampul Associates Architect13334
Tianli Construction Ltd486459
Total paid499793

Headquarters

Project approval date: 2002-11-02

Project location: Port Louis

Project description:
MA headquarters (including all facilities) and laying of a pitch.

Goal project number: 1

Project status: Active

Objectives:
To have a structure capable of implementing a development programme for football in Mauritius. Improve training/playing facilities of the association.

Goal contribution400000
FAP contribution166476
MA contribution0
Other contribution13000
Total budget566476
ContractorsTotal amount
J.Annauth Construction Ltd541566
J & A Architects Ltd37910
Total paid579476