Project approval date: 2013-03-18

Project location: Ta' Qali, Malta

Project description:
Furnishing of 3rd floor of Millenium Stand (Nat. Stadium); incorporating football museum, catering facilities for daily visitors to museum and match day corporate hospitality

Goal project number: 4

Project status: Active

Objectives:
• Turn existing available spaces into football promotion opportunities in order to increase the quality of service provided and marketing possibilities for non-match days
• Incorporate a museum in the stadium

Goal contribution500000
FAP contribution0
MA contribution250000
Other contribution0
Total budget750000

Headquarters

Project approval date: 2008-10-22

Project location: Ta’Qali

Project description:
Purchase of equipment for the Headquarters / National Stadium upgrade.

Goal project number: 3

Project status: Active

Objectives:
The objective of this project is:
- to enable the association to use the technical centre for the training of youth teams

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Malta FA - Purchase of equipment for HQ/Stadium upgrade400000
Total paid400000

Headquarters

Project approval date: 2006-03-15

Project location: Ta’Qali

Project description:
Construction of new headquarters in Ta’Qali

Goal project number: 2

Project status: Active

Objectives:
The objective of this project is:
- to deliver new headquarters and administrative offices befitting a football association

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Malta Football Association400000
Total paid400000

Other

Project location: Ta’Qali

Project description:
Renovation of spectators’ stands in the national stadium in Ta’Qali.

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
- to guarantee modern and safe infrastructure

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Joseph Sammut163500
Mangion Brothers67600
Whitefrost Co.168900
Total paid400000