Project approval date: 2014-09-23

Project description:
Proceed and continue with phase II of the construction of Goal Project III (an indoor hall with one full-sized futsal court, changing rooms, reception area and other related facilities).

Goal project number: 4

Project status: Active

Objectives:
• Host regional and national futsal competitions.
• Train national futsal teams.

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000

Other

Project approval date: 2009-12-01

Project location: Petaling Jaya

Project description:
Construction of an indoor futsal hall. The project includes: a full-sized futsal pitch, changing rooms and a reception area

Goal project number: 3

Project status: Active

Objectives:
The objective of this project is:
-to host regional and national futsal competitions

Goal contribution400000
FAP contribution5133
MA contribution0
Other contribution0
Total budget405133
ContractorsTotal amount
Pembinaan Jaya SDN.BHD.199664
BC Projects SDN.BHD.21637
Total paid221301

Football pitch

Project approval date: 2006-12-03

Project location: Kuala Lumpur

Project description:
Installation of an artificial turf pitch at the national sports school

Goal project number: 2

Project status: Active

Objectives:
The objective of this project is:
-to maximise usage of the facility throughout the year and under all weather conditions for youth team training and competitions

Goal contribution400000
FAP contribution210020
MA contribution0
Other contribution68955
Total budget610020
ContractorsTotal amount
EdelGrass B.V.306650
Light Style Sdn Bhd361325
Realsport s.a.r.l.11000
Total paid678975

Football pitch

Project approval date: 2003-10-15

Project location: Petaling Jaya

Project description:
Installation of an artificial turf pitch at the technical centre. The project includes: floodlights

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
-to maximise usage of the facility throughout the year and under all weather conditions for youth team training and competitions

Goal contribution400000
FAP contribution242731
MA contribution300000
Other contribution0
Total budget942731
ContractorsTotal amount
Gamal Arkitek (installation of floodlights)4000
System Letronik Maju Sdn Bhd (Installation of flood light system)188684
Markus Keller, realsport s.a.r.l.20047
Edel Grass b.v.430000
Total paid642731