Football academy
Project approval date: 2013-03-18
Project location: Carion Technical Centre
Project description:
Support for the creation and sustainability of a football academy at the Carion Technical Centre (Goal II and IV).
Goal project number: 4
Project status: Active
Objectives:
Financial, administrative and technical support for the creation of a football academy with the following aims:
1) Prepare a competitive U-17 team for the African U-17 Championship 2017 to be held in Madagascar
2) Further develop youth football as a strategic pillar for the future
3) Develop technical expertise at local level via targeted support for youth football (qualified coach)
4) Improve the existing infrastructure as financed by the Goal project (technical centre)
The project will be implemented simultaneously with the PERFORMANCE Programme, which will focus on the sustainability of the project from an administrative and financial perspective (marketing).
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
Football pitch
Project approval date: 2010-03-15
Project location: Antananarivo
Project description:
Completion of the work initiated under Goal project I. Installation of an artificial turf pitch at the technical centre in Carion
Goal project number: 3
Project status: Active
Objectives:
The objectives of this project are:
-to complete the previous projects carried out by the association and FIFA
-to improve the preparation of all national teams
| Goal contribution | 400000 |
| FAP contribution | 23000 |
| MA contribution | 0 |
| Other contribution | 120000 |
| Total budget | 423000 |
| Contractors | Total amount |
|---|---|
| DESSO Sports Systems , Netherlands | 542747 |
| Total paid | 542747 |
Other
Project approval date: 2008-02-04
Project location: Majunga
Project description:
Renovation of the spectator stands and other facilities at the Municipal stadium of Rabemananjara
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
-to upgrade the infrastructure with modern facilities
-to promote football
- to guarantee the security of spectators
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 36297 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| Entreprise Générale de Construction Hatim | 397708 |
| SBTP - Commune Mahajanga | 3200 |
| Entreprise Générale de Construction Hatim | 33452 |
| Total paid | 434360 |
Technical centre
Project approval date: 2002-03-01
Project location: Antananarivo
Project description:
Construction of a technical centre in Carion. The project includes: rooms, a kitchen, a restaurant, conference rooms and administrative offices
Goal project number: 2
Project status: Active
Objectives:
The objective of this project is:
-to develop the preparation and training of players, coaches and referees
| Goal contribution | 56320 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 620719 |
| Total budget | 56320 |
| Contractors | Total amount |
|---|---|
| Atelier Sildy | 3167 |
| Abry Hydro | 40657 |
| Etudes des Infrastructures et Surveillances des Travaux | 15000 |
| EGCOM | 14576 |
| EGCOM | 35563 |
| Fed. Malagasy Football | 20476 |
| Room Show | 19189 |
| Entreprise Ranaivoson | 39199 |
| Andriamanjato John Edgard EGCOM | 371948 |
| Sport Organisation International | 20500 |
| Abri Hydro | 84994 |
| Sport Organisation International | 11770 |
| Total paid | 677039 |
Headquarters
Project location: Antananarivo
Project description:
Rehabilitation of an existing building in Antananarivo to be used as the national association’s headquarters
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
-to deliver headquarters and administrative offices befitting a football association
| Goal contribution | 443681 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 443681 |
| Contractors | Total amount |
|---|---|
| Imob Conseil | 92552 |
| Jary Architectes | 14250 |
| Federation Malagasy de Football | 12000 |
| EGCOM | 74014 |
| IZE | 26872 |
| SBM Banque | 176207 |
| Entreprise RANAIVOSON G: | 15756 |
| SOMEEIM | 25000 |
| Telecom Malagasy | 7030 |
| Total paid | 443681 |