Technical centre
Project approval date: 2012-09-25
Project location: Vientiane
Project description:
Construction of a building to house offices, rooms and a fitness centre.
Goal project number: 5
Project status: Active
Objectives:
This project will help to enhance and strengthen the image of football and will provide
- additional office space for LFF staff for the increasing needs
- a fitness centre for all National Team
- a venue for theoretical sessions (courses, seminars, training camps)
| Goal contribution | 500000 |
| FAP contribution | 22554 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 522554 |
Football pitch
Project approval date: 2010-03-15
Project location: Vientiane
Project description:
Installation of an artificial turf pitch at the national technical centre
Goal project number: 4
Project status: Active
Objectives:
The objective of this project is:
-to enable the association to use the technical centre for the training of all of its national teams
| Goal contribution | 400000 |
| FAP contribution | 100000 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
| Contractors | Total amount |
|---|---|
| Additional drainage costs (Limonta Sports Spa) | 14000 |
| Limonta Sports Spa | 486000 |
| Total paid | 500000 |
Technical centre
Project approval date: 2008-02-04
Project location: Vientiane
Project description:
Construction of the women’s football technical centre. The project includes: a football pitch, a dormitory, a canteen and an office
Goal project number: 3
Project status: Active
Objectives:
The objective of this project is:
-to introduce and develop women’s football in the country
-to be used for other football-related activities
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 22137 |
| Other contribution | 0 |
| Total budget | 422137 |
| Contractors | Total amount |
|---|---|
| KKPS Civil Engineering Co. Ltd | 395000 |
| View Tech Survey, Design Consultant & Construction Co Ltd | 5000 |
| Total paid | 400000 |
Headquarters
Project approval date: 2006-03-15
Project location: Vientiane
Project description:
Construction of the association’s headquarters. The project includes administrative rooms, offices and an indoor futsal stadium
Goal project number: 2
Project status: Active
Objectives:
The objective of this project is:
-to deliver headquarters and administrative offices befitting a football association
-to provide the association with adequate facilities for the preparation and training of the national futsal teams
-to organise courses
| Goal contribution | 400000 |
| FAP contribution | 34846 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 434846 |
| Contractors | Total amount |
|---|---|
| Inpeng Construction Company Ltd. | 418121 |
| Chitakone Enterprise for Architect Design Co. Ltd. | 16725 |
| Total paid | 434846 |
Technical centre
Project approval date: 2000-08-03
Project location: Vientiane
Project description:
Construction of a technical centre. The project includes: two football pitches
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
-to reduce costs
| Goal contribution | 399992 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 399992 |
| Contractors | Total amount |
|---|---|
| DM Construction | 399992 |
| Total paid | 399992 |