Football pitch
Project location: Almaty
Project description:
Installation of an artificial turf pitch at the technical centre
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
- to maximise usage of the facility throughout the year and under all weather conditions for training and competitions of youth teams
| Goal contribution | 390000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 390000 |
| Contractors | Total amount |
|---|---|
| Field Turf | 390000 |
| Total paid | 390000 |