  • Project approval date: 2014-09-23
  • Project location:
  • Project description:
    Construction of facilities including 3,000 seat stands, changing rooms, referee room, public bathrooms, administration rooms at al Hussein Sports City in Amman.(phase 2).
  • Goal project number: 6
  • Project status: Active
  • Objectives:
    • Have a fully functional technical centre.
    • Enhance the training facilities to be used for training of national teams, local clubs and provide a suitable ground for hosting local matches.
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
Total paid0

Technical centre

  • Project approval date: 2012-09-25
  • Project location: Amman
  • Project description:
    Construction of facilities including 3,000 seat stands, changing rooms, referee room, public bathrooms, administration rooms at al Hussein Sports City in Amman.
  • Goal project number: 5
  • Project status: Active
  • Objectives:
    To enhance the training facilities to be used for training of national teams, local clubs and to provide a suitable ground for hosting local matches.
    This project will assist the implementation of JFA’s development plan through the provision of appropriate infrastructure.
Goal contribution500000
FAP contribution83
MA contribution0
Other contribution0
Total budget500083
ContractorsTotal amount
Bashar Engineering Company for Contracting396378
Sabeel Al Handaseh Consultant Engineers56875
Total paid453253

Other

  • Project approval date: 2010-10-26
  • Project location: Al Hussein Sport city, Amman
  • Project description:
    Installation of floodlights and changing rooms at the two football pitches at Al Hussein sports city
  • Goal project number: 4
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to use the facility for night training
Goal contribution400000
FAP contribution1000
MA contribution0
Other contribution0
Total budget401000
ContractorsTotal amount
Delma Construcction Company400000
Abdul Rahem Surour Engineering Corporation1000
Total paid401000

Football pitch

  • Project approval date: 2007-03-21
  • Project location: Amman
  • Project description:
    Installation of an artificial turf pitch at the Al Hussain sport city in Amman. The project includes: floodlights and changing rooms
  • Goal project number: 3
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to maximise usage of the facility throughout the year and under all weather conditions
Goal contribution400000
FAP contribution358866
MA contribution0
Other contribution134334
Total budget758866
ContractorsTotal amount
EdelGrass514800
Realsport13000
EdelGrass (contract between JFA and Edelgrass)365400
Total paid893200

Other

  • Project approval date: 2004-02-17
  • Project location: Amman
  • Project description:
    Construction of a training and fitness centre for national teams in Amman
  • Goal project number: 2
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to provide the association with its own training and fitness centre for the national and club teams
Goal contribution400000
FAP contribution416926
MA contribution0
Other contribution0
Total budget816926
ContractorsTotal amount
Jordan Football Association21096
Faisal: Supplying of Fitness Equipment - 2nd Goal Project189860
Tahaineh: Execution of Fitness Centre for the Jordan FA - 2nd Goal Project605970
Total paid816926

Headquarters

  • Project approval date:
  • Project location: Amman
  • Project description:
    Headquarters in Al Hussain sport city
  • Goal project number: 1
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to deliver headquarters and administrative offices befitting a football association
Goal contribution530000
FAP contribution237479
MA contribution0
Other contribution0
Total budget767479
ContractorsTotal amount
Habash Deir (USD 652'212 + USD 115'267)767479
Total paid767479