Technical centre
Project approval date: 2012-09-25
Project location: Shfaim
Project description:
Completion of the training centre in Shfaim (purchase of furniture, fitness and storage rooms, and construction of the second floor).
Goal project number: 4
Project status: Active
Objectives:
- Improve development programmes and football training, for youth and grassroots activities in particular
- Increase the number of training camps
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 5175676 |
| Other contribution | 0 |
| Total budget | 5675676 |
| Contractors | Total amount |
|---|---|
| Israel FF - Purchase of Equipment for TC Shfaim | 372736 |
| Total paid | 372736 |
Football pitch
Project approval date: 2008-02-04
Project location: Shefayim
Project description:
Installation of an artificial turf pitch at the technical centre
Goal project number: 3
Project status: Active
Objectives:
The objective of this project is:
- to support the clubs with adequate infrastructure
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| second lump-sum payment USD 400000 | 400000 |
| Total paid | 400000 |
Football pitch
Project approval date: 2008-02-04
Project location: Nazareth
Project description:
Installation of a football pitch for local clubs
Goal project number: 2
Project status: Active
Objectives:
The objective of this project is:
- to support clubs with adequate infrastructure
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| Israel Football Federation | 400000 |
| Total paid | 400000 |
Football pitch
Project approval date: 2002-11-02
Project location: Nazareth
Project description:
Installation of an artificial turf pitch
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
- to provide the association and local clubs with a pitch for training purposes
- to maximise usage of the facility throughout the year and under any weather condition
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 40000 |
| Other contribution | 0 |
| Total budget | 440000 |
| Contractors | Total amount |
|---|---|
| Lano Sports | 400000 |
| Total paid | 400000 |