Headquarters

Project approval date: 2004-02-17

Project location: Budapest

Project description: Construction of the association’s headquarters

Goal project number: 1

Project status:

Objectives: The objective of this project is:
- to deliver headquarters and administrative offices befitting a football association

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution2500000
Total budget2900000
ContractorsTotal amount
Office Line Ltd (contract 170'000 + 20% VAT = 34'000 USD)206746
UNITIS Systemhouse Pte Ltd145826
InfoScren Kft48510
Total paid401082

Technical centre

Project approval date: 2006-12-03

Project location: Telki, Budapest

Project description: Construction work to complete the MLSZ technical centre

Goal project number: 2

Project status:

Objectives: The objectives of this project are:
- to enable the association to use the technical centre for the training of its youth and national teams
- to provide a venue for training courses

Goal contribution400000
FAP contribution0
MA contribution2000000
Other contribution3000000
Total budget5400000
ContractorsTotal amount
Contract with Hungarian FA400000
Total paid400000

Technical centre

Project approval date: 2008-02-04

Project location: Telki

Project description: Constructions work to complete the MLSZ technical centre. The project includes: three pitches, a covered hall, accommodation and social premises

Goal project number: 3

Project status:

Objectives: The objective of this project is:
- to enable the association to use the technical centre for the training of its teams

Goal contribution400000
FAP contribution0
MA contribution2000000
Other contribution3000000
Total budget5400000
ContractorsTotal amount
Contract with Hungarian FA400000
Total paid400000