Headquarters
Project approval date: 2013-03-18
Project location: Kowloon, Hong Kong
Project description:
Renovation and refurbishment of the Headquarters of the Hong Kong Football Association in Kowloon, Hong Kong.
Goal project number: 2
Project status: Active
Objectives:
Provide additional and improved office accommodation for the HKFA staff
Create a better working environment that reflects the new organisational structure
Have more office space in order to develop football in a bigger way
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
Headquarters
Project approval date: 2003-10-15
Project location: Kowloon
Project description:
Renovation of the association’s headquarters. The project includes: structural maintenance work
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
-to provide better administration facilities
-to improve the working environment
-to maximise space in the storage area
| Goal contribution | 400000 |
| FAP contribution | 406923 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 806923 |
| Contractors | Total amount |
|---|---|
| New Progress Construction Company Ltd, Kowloon, Hong Kong | 794102 |
| R Cheng Property Consultants Ltd, Kowloon, Hong Kong | 12820 |
| Total paid | 806923 |