Headquarters
Project approval date: 2012-03-27
Project location: Conakry
Project description:
Construction of the headquarters
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
- to assimilate the various bodies and members of the Guinean FA
- to enhance the association’s visibility and profile
- to ensure the autonomy of the Guinean FA
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
| Contractors | Total amount |
|---|---|
| Societe Matcom Sarl | 105280 |
| Arias /Archigram Sarl | 9149 |
| Total paid | 114428 |
Technical centre
Project approval date: 2000-08-03
Project location: Conakry
Project description:
Construction of a technical centre
Goal project number: 1
Project status: Active
Objectives:
The objective of this project is:
- to organise courses, seminars and activities for the development of youth and women’s football
| Goal contribution | 400000 |
| FAP contribution | 184737 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 584737 |
| Contractors | Total amount |
|---|---|
| Bureau Africain d'Architecture, d'Amenagement et Decoration | 33098 |
| Henan Chine | 551639 |
| Total paid | 584737 |