Technical centre
Project approval date: 2012-09-25
Project location: Guatemala
Project description:
Upgrade of the technical centre in Guatemala City, which was constructed with funds from the previous Goal projects.
Goal project number: 5
Project status: Active
Objectives:
This project is intended to further improve the facility.
It increases the MA's capacity and enables them to receive a larger number of players and to develop the players and national teams.
| Goal contribution | 500000 |
| FAP contribution | 1256 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 501256 |
| Contractors | Total amount |
|---|---|
| Carquitectura & Diseño | 48626 |
| Ingeniero José Alejandro Cáceres Sandoval | 1500 |
| Total paid | 50126 |
Technical centre
Project approval date: 2010-10-26
Project location: Guatemala City
Project description:
Completion of the work initiated under Goal projects I and II. The project includes: enlarged dormitories
Goal project number: 4
Project status: Active
Objectives:
The objectives of the project are:
-to increase the accommodation capacity
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| Nilda Marelny Cardona Muñoz | 20000 |
| Arte y Construccion S.A. | 380000 |
| Total paid | 400000 |
Headquarters
Project approval date: 2006-12-03
Project location: Guatemala City
Project description:
Completion of the work initiated under Goal project I. The project includes: dressing rooms, a gymnasium, a football clinic and a football pitch
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
-to provide the association with better facilities
-to host training
-to improve women’s football
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| Arte y Construcción S. A. | 400000 |
| Total paid | 400000 |
Headquarters
Project location: Guatemala City
Project description:
Construction of the technical centre at the national headquarters. The project includes: football pitches and a hotel in Guatemala City
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
-to improve the training of the national teams.
-to organise training sessions for coaches, referees
| Goal contribution | 400000 |
| FAP contribution | 249920 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 649920 |
| Contractors | Total amount |
|---|---|
| Artyco | 649920 |
| Total paid | 649920 |