Goal projects

Other

Project approval date: 2013-09-03

Project location: Toftir, Faroe Islands

Project description:
The Toftir stadium was constructed in 1990 and needs necessary renovations and extension in order to fulfill the UEFA/FIFA criterias for playing internantional matches

Goal project number: 3

Project status: Active

Objectives:
- To be able to play int. Matches at the stadium (national & clubs teams)

Goal contribution500000
FAP contribution0
MA contribution340000
Other contribution0
Total budget840000

Football pitch

Project approval date: 2010-10-26

Project location: Torshavn

Project description:
Installation of an artificial turf pitch at the Torsvollur national stadium

Goal project number: 2

Project status: Active

Objectives:
The objectives of this project are:
- to improve the development and education of players
- to improve the training of the national teams

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution218150
Total budget400000
ContractorsTotal amount
Polytan Sportstättenbau GmbH (VAT payment)122380
Polytan Sportstättenbau GmbH495770
Total paid618150

Headquarters

Project approval date: 2000-08-03

Project location: Torshavn

Project description:
Construction of a four-storey building as the national association’s headquarters

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
- to centralise the activities of the association

Goal contribution400000
FAP contribution350000
MA contribution640000
Other contribution0
Total budget2041000
ContractorsTotal amount
Faroe Football Federation14202
Guttesen/Stakberg735798
Total paid750000