Goal projects

Project approval date: 2011-10-18

Project location: Suva

Project description:
Completion of the work initiated under Goal project II. The project includes: an international standard natural turf pitch and synthetic carpet covering for futsal pitches

Goal project number: 3

Project status: Active

Objectives:
The objectives of this project are:
-to upgrade the existing facilities for the delivery of technical activities
-to support the technical activities and programmes of the national football academy
-to facilitate additional competitions for football and futsal
-to increase opportunities for youth players to participate in organised elite player development programmes
- to facilitate training programmes for national team players (all levels) on a regional basis

Goal contribution500000
FAP contribution6260
MA contribution0
Other contribution0
Total budget506260
ContractorsTotal amount
Vuksich & Borich (NZ) Lim. - Natural Turf446634
Design Hut (Architects)10000
Total paid456634

Headquarters

Project approval date: 2005-02-17

Project location: Suva

Project description:
Headquarters and regional technical centre. The project includes: administration offices, accommodation, an education centre, dining and kitchen facilities and a futsal pitch

Goal project number: 2

Project status: Active

Objectives:
The objectives of this project are:
-to deliver headquarters and administrative offices befitting a football association
-to enhance delivery of services and programmes
-to complement the technical activities and programmes of the national football academy
-to establish futsal playing facilities, new competitions and expansion of the game

Goal contribution400000
FAP contribution100000
MA contribution130000
Other contribution0
Total budget680000
ContractorsTotal amount
Fortech Construction Ltd.500000
Total paid500000

Technical centre

Project approval date: 2001-07-04

Project location: Ba

Project description:
National football academy. The project includes: two natural turf pitches, accommodation, an education centre, dining and kitchen facilities and administration offices

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
- to train and prepare the national teams at all levels
- to deliver elite player development programmes
- to deliver national and regional educational courses for coaches, referees and administrators
-to facilitate local, regional and national competition matches (all categories and levels)

Goal contribution400000
FAP contribution152550
MA contribution0
Other contribution0
Total budget552550
ContractorsTotal amount
Ashok Balgovind552550
Total paid552550