Project approval date: 2011-10-18
Project location: Suva
Project description:
Completion of the work initiated under Goal project II. The project includes: an international standard natural turf pitch and synthetic carpet covering for futsal pitches
Goal project number: 3
Project status: Active
Objectives:
The objectives of this project are:
-to upgrade the existing facilities for the delivery of technical activities
-to support the technical activities and programmes of the national football academy
-to facilitate additional competitions for football and futsal
-to increase opportunities for youth players to participate in organised elite player development programmes
- to facilitate training programmes for national team players (all levels) on a regional basis
| Goal contribution | 500000 |
| FAP contribution | 6260 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 506260 |
| Contractors | Total amount |
|---|---|
| Vuksich & Borich (NZ) Lim. - Natural Turf | 296873 |
| Design Hut (Architects) | 1000 |
| Total paid | 297873 |
Headquarters
Project approval date: 2005-02-17
Project location: Suva
Project description:
Headquarters and regional technical centre. The project includes: administration offices, accommodation, an education centre, dining and kitchen facilities and a futsal pitch
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
-to deliver headquarters and administrative offices befitting a football association
-to enhance delivery of services and programmes
-to complement the technical activities and programmes of the national football academy
-to establish futsal playing facilities, new competitions and expansion of the game
| Goal contribution | 400000 |
| FAP contribution | 100000 |
| MA contribution | 130000 |
| Other contribution | 0 |
| Total budget | 680000 |
| Contractors | Total amount |
|---|---|
| Fortech Construction Ltd. | 500000 |
| Total paid | 500000 |
Technical centre
Project approval date: 2001-07-04
Project location: Ba
Project description:
National football academy. The project includes: two natural turf pitches, accommodation, an education centre, dining and kitchen facilities and administration offices
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
- to train and prepare the national teams at all levels
- to deliver elite player development programmes
- to deliver national and regional educational courses for coaches, referees and administrators
-to facilitate local, regional and national competition matches (all categories and levels)
| Goal contribution | 400000 |
| FAP contribution | 152550 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 552550 |
| Contractors | Total amount |
|---|---|
| Ashok Balgovind | 552550 |
| Total paid | 552550 |