  • Project approval date: 2014-03-19
  • Project location: Sal Island
  • Project description:
    Construction of a Regional Technical Centre on Sal Island.
  • Goal project number: 4
  • Project status: Active
  • Objectives:
    Build a Regional Technical Centre on Sal Island (northern Barlavento Islands), with the following objectives:

    1) Decentralise football development.
    2) Organise grassroots activities.
    3) Enable the training of young players (boys and girls).
    4) Enable the organisation of local league matches.
    5) Improve football infrastructure on all the islands of the archipelago.
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
Total paid0

Technical centre

  • Project approval date: 2007-03-21
  • Project location: Mindelo
  • Project description:
    Construction of a regional technical centre
  • Goal project number: 3
  • Project status: Active
  • Objectives:
    The objective of this project is:
    - to organise courses, seminars and activities for the development of youth and women’s football
Goal contribution400000
FAP contribution700000
MA contribution0
Other contribution100000
Total budget1100000
ContractorsTotal amount
Armando Cunha, Sucursal Cabo Verde920150
Antonio Bernardo Nascimento, Ministerio das Insfrastruturas e Economia Maritima61416
Total paid981566

Football pitch

  • Project approval date: 2004-02-17
  • Project location: Praia
  • Project description:
    Installation of an artificial turf pitch at the technical centre. The project includes sports equipment
  • Goal project number: 2
  • Project status: Active
  • Objectives:
    The objectives of this project are:
    - to develop youth training programmes at national level
    - to complete and develop the previous projects carried out by the association and FIFA
Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Markus Keller1209
Realsport SARL7278
Sport organisation International104715
Lano Sports N.V.286798
Total paid400000

Headquarters

  • Project approval date: 2001-07-04
  • Project location: Praia
  • Project description:
    Construction of the headquarters and the technical centre
  • Goal project number: 1
  • Project status: Active
  • Objectives:
    The objectives of this project are:
    - to deliver the headquarters and a technical centre befitting a football association
    - to organise courses, seminars and activities for the development of youth and women’s football
Goal contribution400000
FAP contribution471233
MA contribution0
Other contribution0
Total budget871233
ContractorsTotal amount
ENGEOBRA829760
Henri GOMES41475
Total paid871235