Goal projects

Football pitch

Project approval date: 2014-03-19

Project location: Moroni

Project description:
Installation of a football turf pitch at the national stadium in Moroni, Comoros Islands.

Goal project number: 5

Project status: Active

Objectives:
install an artificial turf at the national stadium in Moroni, with the following objectives:

1) Improve the overall quality of the football pitches in the country.
2) Enable a sustained use of the national stadium for the national league (first and second division).
3) Reduce costs (water and maintenance).
4) Expand activities in the domain of junior and women’s football.

Goal contribution500000
FAP contribution140175
MA contribution0
Other contribution0
Total budget640175
ContractorsTotal amount
Edel Grass B.V.416508
Total paid416508

Other

Project approval date: 2011-10-18

Project location: Grande Comore island, Anjouan island, Moheli island

Project description:
The project consists of two parts: the renovation of three football pitches and the construction of a main spectator stand in the Moroni Stadium and the activation of the “TWAMAYA” football academy

Goal project number: 4

Project status: Active

Objectives:
The objectives of this project are:
-to upgrade the football pitches in the stadium
-to improve training conditions for players
-to ensure the development of youth football

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Entreprise Ecrebat40025
E.R.T.A: Ingenieriel- Conseils, Comores8823
A.R.C, Comores79578
Entreprise Said Hassane Fils81143
MA (Football academy)250061
Somocor (Omar Ben Hassan Ali)40370
Total paid500000

Technical centre

Project approval date: 2009-06-02

Project location: Grande Comore island, Anjouan island, Moheli island

Project description:
Renovation and rehabilitation of existing football facilities in three different venues. The project consists of: rehabilitation of three football pitches in Comoros (1 in Anjouan, 1 in Moheli and 1 in Grande Comore) and renovation of a technical centre in Moheli. It also includes fitness and football equipment for the national technical centre in Mitsamouili

Goal project number: 3

Project status: Active

Objectives:
The objective of this project is:
-to allow the association to organise courses, seminars and activities in the technical centre

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
EDEC Entreprise (terrain Sima - Anjouan)31437
Fédération Comorienne de Football119992
SAID Hassane Fils (facture)16000
SCPMC (terrain de Moroni)42857
SOMOCOR (terrain Wanani - Moheli)34284
SOMOCOR (siège Moheli)35429
Fédération Comorienne de Football120000
Total paid400000

Football academy

Project approval date: 2007-03-24

Project location: Grande Comore

Project description:
Completion of the “TWAMAYA” national football academy in Mitsamiouli (North of Grande Comore)

Goal project number: 2

Project status: Active

Objectives:
The objectives of the project are:
-to provide the national football academy with the onlystadium in the country, which has comfortable accommodation for the national teams, and teaching and meeting rooms

Goal contribution400000
FAP contribution116637
MA contribution0
Other contribution0
Total budget516637
ContractorsTotal amount
Said Hassane et Fils110000
Maison Souleimana120000
Said Hassane et fils12130
Atelier Sildy24541
Said Hassane et fils96970
SOGECOM35000
ARC ingenieurs Conseils35000
Said Hassane et fils2996
Said Hassane et fils80000
Total paid516637

Headquarters

Project approval date: 2005-11-07

Project location: Grande Comore

Project description:
Construction of the national association’s headquarters in Moroni and of the national “TWAMAYA” football academy in Mitsamiouli (North of Grande Comore)

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
-to deliver headquarters and administrative offices befitting a football association
-to organise courses, seminars and activities for the development of youth football

Goal contribution398920
FAP contribution0
MA contribution0
Other contribution0
Total budget398920
ContractorsTotal amount
Maison des Consommables Bureautiques9300
SEDACO270700
Maison Soulaimana77000
ARC ingenieur conseil25000
Hachim Freres16920
Total paid398920