Project approval date: 2011-10-18
Project location: Grande Comore island, Anjouan island, Moheli island
Project description:
The project consists of two parts: the renovation of three football pitches and the construction of a main spectator stand in the Moroni Stadium and the activation of the “TWAMAYA” football academy
Goal project number: 4
Project status: Active
Objectives:
The objectives of this project are:
-to upgrade the football pitches in the stadium
-to improve training conditions for players
-to ensure the development of youth football
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
| Contractors | Total amount |
|---|---|
| Entreprise Ecrebat | 36022 |
| E.R.T.A: Ingenieriel- Conseils, Comores | 7057 |
| A.R.C, Comores | 71620 |
| Entreprise Said Hassane Fils | 81232 |
| MA (Football academy) | 250061 |
| Somocor (Omar Ben Hassan Ali) | 20183 |
| Total paid | 465294 |
Technical centre
Project approval date: 2009-06-02
Project location: Grande Comore island, Anjouan island, Moheli island
Project description:
Renovation and rehabilitation of existing football facilities in three different venues. The project consists of: rehabilitation of three football pitches in Comoros (1 in Anjouan, 1 in Moheli and 1 in Grande Comore) and renovation of a technical centre in Moheli. It also includes fitness and football equipment for the national technical centre in Mitsamouili
Goal project number: 3
Project status: Active
Objectives:
The objective of this project is:
-to allow the association to organise courses, seminars and activities in the technical centre
| Goal contribution | 400000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 400000 |
| Contractors | Total amount |
|---|---|
| EDEC Entreprise (terrain Sima - Anjouan) | 31437 |
| Fédération Comorienne de Football | 119992 |
| SAID Hassane Fils (facture) | 16000 |
| SCPMC (terrain de Moroni) | 42857 |
| SOMOCOR (terrain Wanani - Moheli) | 34284 |
| SOMOCOR (siège Moheli) | 35429 |
| Fédération Comorienne de Football | 120000 |
| Total paid | 400000 |
Football academy
Project approval date: 2007-03-24
Project location: Grande Comore
Project description:
Completion of the “TWAMAYA” national football academy in Mitsamiouli (North of Grande Comore)
Goal project number: 2
Project status: Active
Objectives:
The objectives of the project are:
-to provide the national football academy with the onlystadium in the country, which has comfortable accommodation for the national teams, and teaching and meeting rooms
| Goal contribution | 400000 |
| FAP contribution | 116637 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 516637 |
| Contractors | Total amount |
|---|---|
| Said Hassane et Fils | 110000 |
| Maison Souleimana | 108000 |
| Said Hassane et fils | 12130 |
| Atelier Sildy | 24541 |
| Said Hassane et fils | 96970 |
| SOGECOM | 35000 |
| ARC ingenieurs Conseils | 35000 |
| Said Hassane et fils | 2996 |
| Said Hassane et fils | 80000 |
| Total paid | 504637 |
Headquarters
Project approval date: 2005-11-07
Project location: Grande Comore
Project description:
Construction of the national association’s headquarters in Moroni and of the national “TWAMAYA” football academy in Mitsamiouli (North of Grande Comore)
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
-to deliver headquarters and administrative offices befitting a football association
-to organise courses, seminars and activities for the development of youth football
| Goal contribution | 398920 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 398920 |
| Contractors | Total amount |
|---|---|
| Maison des Consommables Bureautiques | 9300 |
| SEDACO | 270700 |
| Maison Soulaimana | 77000 |
| ARC ingenieur conseil | 25000 |
| Hachim Freres | 16920 |
| Total paid | 398920 |