Goal projects

Technical centre

Project approval date: 2012-09-25

Project location: Bogota

Project description:
National technical centre (3 football fields, reconstruction of changing rooms and 3-floor building to be used as hotel and offices).

Goal project number: 2

Project status: Active

Objectives:
The objective of this project is to provide the MA with adequate facilities to prepare for their national teams and to lower costs of hotel accommodation for national teams. This project will allow the completion of the second phase of the building,

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Union Temporal Colombia 2014476190
A&N Estructuras Metalicas Construccion y Consultoria23810
Total paid500000

Technical centre

Project approval date: 2003-05-01

Project location: Bogota

Project description:
Construction of the national technical centre. The project includes: accommodation, an auditorium and offices

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
-to provide a venue for the training of the national teams
-to reduce accommodation costs

Goal contribution400000
FAP contribution450000
MA contribution270000
Other contribution0
Total budget1120000
ContractorsTotal amount
Union Temporal Colombia 2014728773
Jorge Nelson Vargas Lopez A&N Estructuras metalicas construccion y consultoria40252
Total paid769025