Goal projects

Project approval date: 2012-03-27

Project location: Rarotonga Aitutaki

Project description:
Completion of the work initiated under previous Goal projects. The project includes: accommodation, dining, kitchen and recreation facilities, accommodation, a gymnasium and furnishings
The project also includes:
construction of administration and technical offices at the regional technical centre in Aitutaki. The project includes: an education centre and accommodation

Goal project number: 5

Project status: Active

Objectives:
The objectives of this project are:
-to provide additional accommodation capacity at the national technical centre in Rarotonga
-to facilitate and improve the residential U-17 talented youth programme that relocates youth players from the outer islands to Rarotonga for a 12-15 month period
-to create a regional technical centre on Aitutaki island to achieve the association’s development strategies
- to provide local development programmes and activities for grassroots and talented youth players (men and women)

Goal contribution500000
FAP contribution2609
MA contribution0
Other contribution0
Total budget502609
ContractorsTotal amount
Williams Contractors - Regional TC Aitutaki Island190130
Goal Football Project C.I.F.A.84376
RomanisDesign Ltd (Architect)11840
Cook Islands Football Association10272
RVK Contractors Limited147945
RVK Contractors Limited2847
Cook Islands Football Association15055
Romanis Design - Regional TC Aitutaki Island19012
Total paid481476

Headquarters

Project approval date: 2010-03-15

Project location: Rarotonga

Project description:
Completion of the work initiated under Goal project I. The project includes: administration and management offices, a gymnasium, equipment, a dormitory, accommodation and upgrading of a natural turf pitch

Goal project number: 4

Project status: Active

Objectives:
The objectives of this project are:
-to improve the quality of the playing and training pitches
-to deliver headquarters and administrative offices befitting a football association
-to provide adequate infrastructure for the organisation of specific technical programmes and activities

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Romanisdesign Ltd16400
Landholdings Ltd222916
CIFA81795
Vuksich & Borich (NZ) Limited78889
Total paid400000

Technical centre

Project approval date: 2008-10-22

Project location: Rarotonga

Project description:
Completion of the work initiated under Goal project II at the national technical centre. The project includes: construction of the tribune (500 seats) and media facilities

Goal project number: 3

Project status: Active

Objectives:
The objectives of this project are:
-to provide adequate facilities for players, match officials, media and the public
-to increase revenue
-to provide independence to implement all football activities – national and local – in the country
-to promote and market football participation through excellence in facilities and activities

Goal contribution399250
FAP contribution0
MA contribution0
Other contribution0
Total budget399250
ContractorsTotal amount
Land Holdings Limited357764
RomanisDesign Limited28236
Vuksich & Borich (NZ) Limited13250
Total paid399250

Technical centre

Project approval date: 2005-11-07

Project location: Rarotonga

Project description:
Extension of the technical centre. The project includes: team and match officials’ changing rooms, media and PA facilities, public toilets and services

Goal project number: 2

Project status: Active

Objectives:
The objectives of this project are:
- to provide adequate facilities for players, match officials, media and the public
-to increase opportunities to participate in organised competitions for all categories
-to provide independence to implement all national and local football activities in the country

Goal contribution400000
FAP contribution44054
MA contribution0
Other contribution0
Total budget444054
ContractorsTotal amount
Romanis Design Ltd17383
Cook Islands Football Association146965
Land Holdings Ltd279706
Total paid444054

Headquarters

Project approval date: 2001-02-13

Project location: Rarotonga

Project description:
Construction of administration and management offices, an education centre, dining and kitchen facilities, changing rooms, accommodation for players and coaches, an international standard natural turf pitch, a training area, maintenance and turf equipment and security fencing

Goal project number: 1

Project status: Active

Objectives:
The objectives of this project are:
- to have ownership and undisrupted access to playing facilities for the establishment of regular competitions
-to provide adequate infrastructure for the training and education of national teams
-to organise courses, youth development and grassroots programmes
-to deliver headquarters and administrative offices befitting a football association

Goal contribution400000
FAP contribution229000
MA contribution0
Other contribution0
Total budget643000
ContractorsTotal amount
Vuksich & Borich 629000
Total paid629000