Follow us on

Goal Programme

Goal projects

Football pitch

  • Project approval date: 2011-10-18
  • Project location: Kinshasa
  • Project description:
    Installation of an artificial turf pitch at the technical centre
  • Goal project number: 6
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to improve the training of the different football teams
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Limonta500000
Total paid500000

Football pitch

  • Project approval date: 2011-02-28
  • Project location: Kinshasa
  • Project description:
    Installation of an artificial turf pitch at the technical centre
  • Goal project number: 5
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to improve the training of the different football teams
Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000
ContractorsTotal amount
Limonta500000
Total paid500000

Football pitch

  • Project approval date: 2010-03-15
  • Project location: Kinshasa
  • Project description:
    Installation of an artificial turf pitch at the Tata Raphael stadium in Kinshasa
  • Goal project number: 4
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to improve the playing conditions and the end results
Goal contribution400000
FAP contribution0
MA contribution0
Other contribution178057
Total budget400000
ContractorsTotal amount
Greenfields578057
Total paid578057

Football pitch

  • Project approval date: 2008-10-22
  • Project location: Lubumbashi
  • Project description:
    Installation of an artificial turf pitch at the Kenya stadium
  • Goal project number: 3
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to improve the playing conditions and the end results
Goal contribution400304
FAP contribution23147
MA contribution0
Other contribution757432
Total budget423451
ContractorsTotal amount
Greenfields BV1157432
Total paid1157432

Headquarters

  • Project approval date: 2005-05-10
  • Project location: Kinshasa
  • Project description:
    Extension of the association’s headquarters and technical centre
  • Goal project number: 2
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to help the association to optimise the use of the headquarters and the technical centre
Goal contribution398979
FAP contribution0
MA contribution0
Other contribution0
Total budget398979
ContractorsTotal amount
Net Clean6529
NJ Construction217800
GRAPI Sprl65000
Cabinet Architecte Noel Kibishingo7750
Noel & Espace Tropical11900
ADIR ONGD90000
Total paid398979

Technical centre

  • Project approval date: 2002-11-02
  • Project location: Kinshasa
  • Project description:
    Construction of the technical centre. The project includes: dormitories, a kitchen and a cafeteria
  • Goal project number: 1
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to enable the association to use the technical centre for the training of all of its national teams
Goal contribution400000
FAP contribution176853
MA contribution0
Other contribution0
Total budget576853
ContractorsTotal amount
Bureau d'etudes40340
UAC SPRL17850
Grapi SPRL479392
Maison Baheyke Quincaillerie39270
Total paid576852