Technical centre
Project approval date: 2011-10-18
Project location: Bati District
Project description:
Purchase and installation of a water filtration system, power supply equipment and other equipment for the cafeteria and dormitories. The project includes: construction of a power supply connection
Goal project number: 4
Project status: Active
Objectives:
The objective of this project are:
-to complete the national technical centre
-to support the training and education of grassroots and youth football teams
-to organise competitions at youth level
| Goal contribution | 500000 |
| FAP contribution | 0 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 500000 |
| Contractors | Total amount |
|---|---|
| Phin Ravudh Team Consultant Co., Ltd. (water) | 23000 |
| Football Federation of Cambodia | 154122 |
| Phin Ravudh Team Consultant Co., Ltd (electric) | 15000 |
| Partner of Construction and Development Services (electric) | 106646 |
| Partner of Construction and Development Services (water) | 169966 |
| Total paid | 468733 |
Technical centre
Project approval date: 2010-10-26
Project location: Bati District
Project description:
Extension of the national technical centre. The project includes: two dormitories and changing rooms
Goal project number: 3
Project status: Active
Objectives:
The objective of this project is:
-to help the association to optimise the use of its technical centre
| Goal contribution | 400000 |
| FAP contribution | 20773 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 420773 |
| Contractors | Total amount |
|---|---|
| Phin Ravudh Team Consultant | 30000 |
| Khmer Nihon Corporation Co Ltd | 390773 |
| Total paid | 420773 |
Technical centre
Project approval date: 2006-03-15
Project location: Bati District
Project description:
Extension of the technical centre
Goal project number: 2
Project status: Active
Objectives:
The objective of this project is:
-to provide additional infrastructure and accommodation facilities for the training of national teams
| Goal contribution | 400000 |
| FAP contribution | 15932 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 415932 |
| Contractors | Total amount |
|---|---|
| Purchase of Turf equipment | 14940 |
| Phin Ravudh Team Consultant | 30000 |
| Khmer Nihong Corporation | 370992 |
| Total paid | 415932 |
Headquarters
Project approval date: 2000-08-03
Project location: Phnom Penh
Project description:
Construction of the association’s headquarters and technical centre
Goal project number: 1
Project status: Active
Objectives:
The objectives of this project are:
-to reduce costs
-to deliver headquarters and administrative offices befitting a football association
-to organise training sessions for the national team
| Goal contribution | 400000 |
| FAP contribution | 40797 |
| MA contribution | 0 |
| Other contribution | 0 |
| Total budget | 440797 |
| Contractors | Total amount |
|---|---|
| Phin Vichearavudh (USD 14'800 - USD 7'800) | 7000 |
| Seng Enterprise | 433797 |
| Total paid | 440797 |