Headquarters

Project approval date: 2005-02-17

Project location: Bandar Seri Begawan

Project description:
Construction of the association’s headquarters. The project includes: administrative offices, meeting rooms and a multi-purpose hall

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
-to deliver headquarters and administrative offices befitting a football association

Goal contribution400000
FAP contribution1199405
MA contribution0
Other contribution0
Total budget1599405
ContractorsTotal amount
LCY Development Sdn Bhd (additinal work)150000
Perunding Alamreka Sdn Bhd92000
LCY Development Sdn Bhd1351248
Total paid1593248