  • Project approval date: 2008-10-22
  • Project location: Cochabamba
  • Project description:
    Completion of the work initiated under Goal Project I. The project includes: administrative offices and equipment
  • Goal project number: 2
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to complete and develop the previous project carried out by the association and FIFA
Goal contribution400000
FAP contribution18627
MA contribution0
Other contribution0
Total budget418627
ContractorsTotal amount
Carpinteria 'Manuel Fernandez'48501
Empresa R.C. Servicios y Ingenieria26439
Empresa Constructora J.G.H.CH.42833
Industria DEMARC Ltda.15948
Empresa Constructora Caceres Aranibar22184
Empresa Constructora J.G. CH.17396
Total paid173302

Technical centre

  • Project approval date: 2000-08-03
  • Project location: Cochabamba
  • Project description:
    Construction of the FBF technical centre in Vinto, Cochabamba
  • Goal project number: 1
  • Project status: Active
  • Objectives:
    The objective of this project is:
    -to have facilities adapted to the needs of national teams, education and development programmes
Goal contribution400000
FAP contribution205228
MA contribution455000
Other contribution0
Total budget1630228
ContractorsTotal amount
ALBOMONTE S.R.L.25500
Empresa R.C. Servicios Técnicos y de Ingeniería43021
Addendum N°2 al contrato Paola Eliana Borda Vega21637
Addendum N°1 al contrato de Paola Eliana Borda Vega28523
Paola Eliana Borda Vega34748
Julio Cesar Quintana T.71800
Sudamericana380000
Total paid605228