Goal projects

Other

Project approval date: 2013-09-03

Project location: Manamah

Project description:
The project will be realized in three phases. The indoor stadium includes:
• Turf football field
• One stand with a capacity for 2000 spectators
• Administrative offices
• Facilities (for players and spectators)

Goal project number: 6

Project status: Active

Objectives:
• Provide indoor facilities with a turf football field to be used during summertime
• Have full integration projects in the complex as well as multipurpose activities

Goal contribution500000
FAP contribution312500
MA contribution0
Other contribution0
Total budget812500

Headquarters

Project approval date: 2010-10-26

Project location: Manamah

Project description:
Construction of a new building at the headquarters. The project includes: offices, seminar rooms, classrooms and an auditorium

Goal project number: 5

Project status: Active

Objectives:
The objectives of this project are:
-to extend the headquarters complex
-to upgrade the existing football infrastructure

Goal contribution400000
FAP contribution225000
MA contribution0
Other contribution0
Total budget625000
ContractorsTotal amount
Bahrain Football Association625000
Total paid625000

Football academy

Project approval date: 2008-10-22

Project location: Manamah

Project description:
This is a pilot project. Talent academy at the technical centre. The project consists of training sessions for players five times a week after school and during school holidays. The academy will provide transportation and food.
The talent academy staff will consist of a full-time head coach, part-time assistant coach and goalkeeper/fitness coach

Goal project number: 4

Project status: Active

Objectives:
The objectives of this project are:
-to provide professional training to talented youth players
- to improve the performance of the youth and men’s national teams
-to fully use the technical centre and its facilities

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution0
Total budget400000
ContractorsTotal amount
Bahrain Football Association400000
Total paid400000

Football pitch

Project approval date: 2007-03-21

Project location: Manamah

Project description:
Installation of two artificial turf pitches at the technical centre

Goal project number: 3

Project status: Active

Objectives:
The objective of this project is:
-to provide the association with training facilities for its youth and women’s teams

Goal contribution400000
FAP contribution532000
MA contribution0
Other contribution0
Total budget932000
ContractorsTotal amount
GreenFields BV (additional work)40000
GreenFields BV882000
Realsport10000
Total paid932000

Technical centre

Project approval date: 2004-09-22

Project location: Manamah

Project description:
Construction of a technical centre in Isa Town

Goal project number: 2

Project status: Active

Objectives:
The objectives of this project are:
-to enable the association to use the technical centre for the training of its various teams and administrative staff
-to organise national camps for the development of football

Goal contribution400000
FAP contribution450000
MA contribution531867
Other contribution0
Total budget1381867
ContractorsTotal amount
Hafeera Contracting Company W.L.L.850000
Total paid850000

Headquarters

Project approval date: 2001-07-04

Project location: Manamah

Project description:
Construction of the association’s headquarters. The project includes: a conference hall and meeting rooms

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
-to deliver headquarters and administrative offices befitting a football association

Goal contribution400000
FAP contribution368200
MA contribution56000
Other contribution0
Total budget824200
ContractorsTotal amount
M&I Construction768200
Total paid768200