Technical centre

Project approval date: 2001-07-04

Project location: Porto Novo and Abomé

Project description: Construction of a technical centre in Porto Novo and a football academy in Abomé

Goal project number: 1

Project status:

Objectives: The objectives of this project are:
- to organise courses, seminars and activities for the development of youth and women’s football
- to ensure the development of young talent

Goal contribution400000
FAP contribution261497
MA contribution0
Other contribution0
Total budget661497
ContractorsTotal amount
Haute Adherence30934
Uni decor29000
Ets Audas21000
Mapolo183618
Perfect396944
Total paid661496

Headquarters

Project approval date: 2006-09-28

Project location: Porto Novo

Project description: Construction of headquarters and installation of new
equipment for the technical centre

Goal project number: 2

Project status:

Objectives: The objectives of this project are:
- to deliver headquarters and administrative offices befitting a football association
- to organise courses, seminars and activities for the development of youth and women’s football

Goal contribution400000
FAP contribution6238
MA contribution0
Other contribution0
Total budget406238
ContractorsTotal amount
SCACU Sarl355038
Haute Adherence20000
Soreco31200
Total paid406238

Technical centre

Project approval date: 2009-06-02

Project location: Porto Novo

Project description: Completion of the national technical centre. The project includes: fencing, a watering system, a power supply and painting

Goal project number: 3

Project status:

Objectives: The objective of this project is:
-to organise courses, seminars and activities for the development of youth and women’s football

Goal contribution400000
FAP contribution122619
MA contribution0
Other contribution0
Total budget522619
ContractorsTotal amount
Narsil43200
Entreprise Haute Adherence10400
Entreprise SORECO212445
Societe Unir International120838
Entreprise ESA Groupe86495
Total paid473377