Goal projects

Football pitch

Project approval date: 2014-03-19

Project location: Gitega stadium

Project description:
Football turf pitch which will be installed in Gitega stadium.

Goal project number: 4

Project status: Active

Objectives:

Install an artificial turf in Gitega (2nd biggest town in Burundi), with the following objectives:

1) Improve the quality of the football pitches for professional football and allow league matches to take place on good surfaces
2) Provide a training ground for local clubs
3) Enable the use of the stadium for national events and youth leagues
4) Expand grassroots and football activities in the whole country

Goal contribution500000
FAP contribution0
MA contribution0
Other contribution0
Total budget500000

Technical centre

Project approval date: 2009-12-01

Project location: Bujumbura

Project description:
Extension of the technical centre. The project includes: football pitches

Goal project number: 3

Project status: Active

Objectives:
The objectives of this project are:
-to help the association to optimise the use of its technical centre

Goal contribution400000
FAP contribution125000
MA contribution0
Other contribution0
Total budget525000
ContractorsTotal amount
Federation de Football du Burundi (FFB)31630
BECIM25000
SEICO340000
Total paid396630

Technical centre

Project approval date: 2007-03-21

Project location: Bujumbura

Project description:
Construction of a technical centre. The project includes: football pitches

Goal project number: 2

Project status: Active

Objectives:
The objective of this project is:
-to provide the association with infrastructure for the training of all the teams

Goal contribution400000
FAP contribution50000
MA contribution0
Other contribution0
Total budget450000
ContractorsTotal amount
Bureau d'Architecture BAMA LTD24237
SEICO COMPANY423268
Total paid447505

Headquarters

Project approval date: 2004-09-22

Project location: Bujumbura

Project description:
Construction of the association’s headquarters

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
-to deliver headquarters and administrative offices befitting a football association

Goal contribution399116
FAP contribution0
MA contribution0
Other contribution0
Total budget399116
ContractorsTotal amount
AGGLOBU308960
Omni Distribution14479
General Trading Services21513
Remondino Architecte23350
O-DIS21500
La Belle Maison9314
Total paid399116