Goal projects

Football pitch

Project approval date: 2010-03-15

Project location: Paynters St. George’s

Project description:
Installation of a football pitch at the technical centre

Goal project number: 3

Project status: Active

Objectives:
The objectives of this project are:
-to provide adequate infrastructures for development programmes for coaches, referees, youth players
-to provide training facilities for the national teams
-to optimise the usage of the existing facility

Goal contribution400000
FAP contribution0
MA contribution0
Other contribution13200
Total budget400000

Technical centre

Project approval date: 2005-11-07

Project location: Paynters St. George’s

Project description:
Completion of the work initiated under Goal project I. The project includes: a new natural turf pitch, external walls, lights, showers and changing rooms

Goal project number: 2

Project status: Active

Objectives:
The objective of this project is:
-to complete and develop the previous projects carried out by the association and FIFA

Goal contribution503098
FAP contribution0
MA contribution100000
Other contribution36800
Total budget603098
ContractorsTotal amount
Pyramid Construction Ltd.493331
Musco Sports Lighting, LLC5167
SBA Consultants41400
Total paid539898

Technical centre

Project approval date: 2000-10-24

Project location: Paynters St. George’s

Project description:
Extension of the technical centre. The project includes: a natural turf pitch, fences and lighting

Goal project number: 1

Project status: Active

Objectives:
The objective of this project is:
-to develop the technical infrastructure with the installation of a natural turf pitch

Goal contribution471364
FAP contribution0
MA contribution0
Other contribution0
Total budget471364
ContractorsTotal amount
Terrance Small4000
Electric Connection467364
Total paid471364